In Tenerife, a full home renovation costs between €500 and €1,500 per square metre. For standard or mid-range finishes, the usual average is between €700 and €1,000/m². For a 70 m² flat, the total cost starts at around €18,000 with basic finishes and can go above €50,000 with premium materials. A complete kitchen ranges from €5,000 to €14,000, a bathroom from €3,000 to €8,500 and the plumbing and electrics from €3,000 to €7,000. The usual timeframe is 2 to 4 months.
That’s the range, and it’s wide for a reason: ‘full renovation’ describes very different things. Replacing the floors, painting and fitting a new kitchen in a flat whose plumbing and electrics are already decent is nothing like stripping a 1960s home back to the brick. Below is the breakdown so you can place your own case before anyone gives you a figure over the phone.
The short answer: cost per square metre
The price per square metre is the most useful way to compare quotes, because it takes the size of the home out of the equation. These are the three levels used on the island:
| Renovation level | Price per m² | What’s included |
|---|---|---|
| Basic | €300–€500/m² | Painting, floors, doors and a light update of the bathroom or kitchen. The plumbing and electrics are not touched. |
| Standard full renovation | €500–€900/m² | New plumbing and electrics, floors, interior doors and joinery, complete kitchen and bathrooms. Same layout. |
| High-end | €900–€1,500/m² | Change of layout, premium materials, climate control, home automation and new windows and external doors. |
If a quote comes in below €300/m² for a home that needs new plumbing and electrics, the question isn’t why it’s so cheap: it’s which line item is missing. It’s almost always the plumbing and electrics, the rubble removal or the permit.
What it costs by the size of your home
Translated into real homes, with the standard range (€500–€900/m²) and high-end shown separately:
| Floor area | Standard renovation | High-end | Timeframe |
|---|---|---|---|
| 50 m² | €25,000–€45,000 | €45,000–€75,000 | 6–9 weeks |
| 70 m² | from €18,000 · €35,000–€63,000 typical | €63,000–€105,000 | 8–12 weeks |
| 90 m² | €45,000–€81,000 | €81,000–€135,000 | 10–14 weeks |
| 120 m² | €60,000–€108,000 | €108,000–€180,000 | 12–16 weeks |
The ‘from €18,000’ for a 70 m² flat applies to basic finishes and a home that doesn’t need its plumbing and electrics completely redone. It’s a genuine market floor, not the price to expect for a full renovation with everything new: for that, look at the standard renovation column.
Price per room: kitchen, bathroom, plumbing and electrics
Many people don’t renovate the whole house at once but tackle it one part at a time. These are the prices for each part on its own in Tenerife:
| Room or item | Price | Notes |
|---|---|---|
| Complete kitchen | €5,000–€14,000 | Depending on the units, the worktop and whether the plumbing and electrics need redoing. Kitchen renovation prices. |
| Complete bathroom | €3,000–€8,500 | 3–5 m², turnkey. Bathroom renovation prices. |
| Plumbing + electrics | €3,000–€7,000 | Whole home, including the electrical installation certificate (boletín). |
| Thermally broken windows and external doors (RPT) | from €380/m² | Windows with a thermal break. In areas exposed to wind and salt air, money well spent. |
| Porcelain tile flooring, laid | €40–€90/m² | Includes material, levelling and labour. Large format is at the top end. |
| Painting the whole home | €8–€16/m² | Measured on wall surface, not floor area. Skimming charged separately. |
A quote broken down line by line
A serious quote is read section by section. This is the approximate share of each section in the total for a standard full renovation, which helps you spot what’s missing from the offers you compare:
- Demolition and rubble removal (8–12%). Includes transport to an authorised tip. If it isn’t there, you’ll pay for it anyway, later.
- Plumbing and electrics (15–20%). Pipework, wiring and the electrical certificate. In homes built before the 1980s, almost always a complete renewal.
- Building work (12–18%). Partition walls, screeds, rendering and levelling of walls.
- Kitchen (15–22%). The item with the widest range in the whole quote.
- Bathrooms (10–18%). Depends a lot on how many there are and whether the sanitaryware is moved.
- Floors and interior joinery (12–18%). Flooring, skirting boards, internal doors and fitted wardrobes.
- Painting and finishing (5–8%). The last thing you see and the first thing you notice if it’s done badly.
- Permits and professional fees (3–6%). Municipal fees, the technical project and site supervision by an architect or engineer (dirección facultativa) when the works require them.
The five variables that move the price
Two quotes for the same home can be €20,000 apart without either of them being dishonest. It almost always comes down to these five things:
- The actual condition of the plumbing and electrics. This is variable number one. A home with iron or lead pipes and a fuse box with no RCD needs new plumbing and electrics, and that’s between €3,000 and €7,000 that isn’t up for debate.
- Whether you change the layout. Knocking down partition walls means a technical project, a major works permit (obra mayor) and more weeks on site. It’s the decision that adds the most cost and also the one that most transforms the result.
- The finishes. Between a mid-range porcelain tile at €40/m² and a large-format one at €90/m², the flooring item doubles. The same goes for the kitchen and the taps.
- Access to the property. A fourth-floor flat with no lift in La Laguna’s historic centre, or a house on a street the lorry can’t get into, pushes up the cost of bringing in materials and taking away the rubble.
- The level of finish. A false ceiling with indirect lighting, concealed skirting or floor-to-ceiling flush doors are aesthetic decisions that add between 10% and 20% to the total.
What renovation you can do with €30,000 or €40,000
They’re the two figures that come up most often on site visits. Translated into actual work:
With €30,000
- A standard full renovation of a 40 to 55 m² home, with everything new.
- Or, in an 80–90 m² flat: complete kitchen, one bathroom, new plumbing and electrics, floors and painting. Left out: the windows and external doors, the second bathroom and any change of layout.
With €40,000
- A standard full renovation of a 55 to 70 m² flat: kitchen, bathrooms, plumbing and electrics, floors, doors and painting.
- Or, in a larger home, all of the above except the windows and external doors and a change of layout.
In both cases the practical advice is the same: prioritise whatever can’t be redone later without opening things up again. The plumbing and electrics and the waterproofing of the bathrooms come first; the designer furniture and the top-of-the-range cooker hood can wait until another year.
Where you can save and where you shouldn’t
Where you can save without it showing two years on:
- Appliances: the difference between mid-range and high-end is rarely justified in everyday use.
- Keeping the existing layout, even if it isn’t perfect.
- Keeping internal doors that are in good condition and lacquering them instead of replacing them.
- Choosing standard tile and flooring sizes instead of large format.
Where it isn’t worth saving:
- Plumbing and electrics. It’s the only thing that, if it fails, means breaking open what you’ve already paid for.
- Waterproofing of shower trays and wet areas.
- Windows and external doors if the home is in a windy area or near the sea: the saving goes on heating, cooling and maintenance.
- The permit. Renovating without one exposes you to enforcement proceedings, a stop-work order and a fine, and makes selling the home more complicated later on.
Once the scope is clear, the next step is to check real prices against your own home: you can get a price for your renovation with a free site visit, or first read what our full home renovation service in Tenerife involves. Before signing with anyone, you’ll also find the guide on how to choose a renovation company useful, and it’s worth checking which building permit you need.
Frequently asked questions
Would you rather have the figure for your own case? Try the renovation cost calculator, which applies these same ranges to your square metres and your finishes. And if what you have is a spending limit rather than a floor area, use what renovation can I do with my budget.
How much does a full renovation cost in Tenerife?
Between €500 and €1,500 per square metre. The average for standard finishes is between €700 and €1,000/m². A 70 m² flat starts at around €18,000 with basic finishes and can go above €50,000 with premium materials.
How much does building work cost per m² in Tenerife?
For renovation – not new build – the range is €500 to €1,500/m² depending on how much work is involved: €300–€500/m² for a basic renovation that leaves the plumbing and electrics alone, €500–€900/m² for a standard full renovation and €900–€1,500/m² for high-end work with a change of layout.
What renovation can I do with €30,000?
A standard full renovation of a 40 to 55 m² home, or a good-quality partial renovation of an 80–90 m² flat: complete kitchen, one bathroom, new plumbing and electrics, floors and painting, leaving out the windows and external doors and any change of layout.
What can I renovate with €40,000?
A standard full renovation of a 55 to 70 m² flat, with complete kitchen and bathrooms, new plumbing and electrics, floors, doors and painting. If the flat is larger, €40,000 covers everything except the windows and external doors and the change of layout.
Does the price include the building permit?
In our quotes, yes: the municipal fees and the technical documentation are included and shown as a line item of their own. It’s worth checking in any quote you compare, because it’s one of the items most often ‘forgotten’ that then turns up on the invoice. You’ll find the details in the guide to building permits in Tenerife.
How long does a full renovation take?
From 2 to 4 months. A 70–90 m² flat with no change of layout usually takes 8–10 weeks; with partition walls demolished and all the plumbing and electrics redone, between 12 and 16 weeks.